In a network diagram using PDM, activity B can start only after activity A has finished. Which dependency type does this represent?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Finish-to-Start (FS)

Finish-to-Start (FS) is the most common dependency, where the successor activity cannot start until the predecessor activity has finished.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Finish-to-Finish (FF)

    Why it's wrong here

    FF means the finish of the successor depends on the finish of the predecessor.

  • Start-to-Finish (SF)

    Why it's wrong here

    SF means the finish of the successor depends on the start of the predecessor.

  • Finish-to-Start (FS)

    Why this is correct

    FS means the successor cannot start until the predecessor finishes.

  • Start-to-Start (SS)

    Why it's wrong here

    SS means the start of the successor depends on the start of the predecessor.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.