PK0-005 Project Management Concepts Practice Question
Who is responsible for providing the project with resources and removing obstacles that are beyond the project manager's control?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project sponsor
The project sponsor provides resources, champions the project, and resolves escalations. The PM manages day-to-day. The steering committee provides governance. The team executes tasks.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project manager
Why it's wrong here
PM manages but does not provide resources.
- ✗
Project team
Why it's wrong here
Team executes tasks.
- ✗
Steering committee
Why it's wrong here
Steering committee provides oversight.
- ✓
Project sponsor
Why this is correct
Sponsor provides resources and removes obstacles.
Visual reference
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.