Project Management Concepts →mediumMultiple Choice

PK0-005 Project Management Concepts Practice Question

A project manager is preparing the stakeholder engagement approach for a hospital construction project. The regulatory authority has high interest and high influence, and can halt the project if permits are delayed. The project manager needs to keep this stakeholder satisfied. Which classification and engagement level is MOST appropriate?

⚠ Common exam trap

The trap here is classifying a regulator as merely influential and therefore only keeping it satisfied, when its active oversight also makes its interest high.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

High interest and high influence, so manage closely through active collaboration.

The power and interest grid places stakeholders into quadrants that drive engagement strategy. When both power and interest are high, the stakeholder must be managed closely with active collaboration. A regulatory authority that can halt construction clearly holds high power and, given its active oversight role, high interest, so close management with proactive communication is the appropriate approach.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    High interest and low influence, so keep informed through regular updates.

    Why it's wrong here

    Keeping a stakeholder informed is appropriate when interest is high but influence is limited. Here the regulator can stop the project, so influence is clearly high. Relying on one-way updates would fail to engage the authority whose approval gates the schedule, leaving a critical dependency unmanaged.

  • ✓

    High interest and high influence, so manage closely through active collaboration.

    Why this is correct

    Stakeholders who are both highly interested and highly influential require close management, meaning active, two-way engagement and early involvement in decisions. For a regulator that can stop the project, this means proactive permit coordination and regular interaction, which is the most effective way to keep the stakeholder satisfied and protect the schedule.

  • ✗

    High influence and low interest, so keep satisfied by addressing their concerns.

    Why it's wrong here

    Keeping a stakeholder satisfied fits those with high influence but low interest, where the goal is to avoid surprises that could trigger interference. The regulator in this scenario is also highly interested, so a minimal-engagement strategy would ignore an actively involved party and miss the chance to resolve permit issues early.

  • ✗

    Low interest and low influence, so monitor with minimal effort.

    Why it's wrong here

    Monitoring with minimal effort suits stakeholders who neither care much nor can affect the outcome. Applying that approach to a regulator that can halt the project would leave permit risks unmanaged. The scenario explicitly states high interest and high influence, so a low-effort monitoring strategy directly contradicts the situation.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.