Courseiva
Project Life CyclehardMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project has an Earned Value (EV) of $50,000, Planned Value (PV) of $60,000, and Actual Cost (AC) of $55,000. What is the cost performance index (CPI) and what does it indicate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

CPI = 0.91; project is over budget

CPI = EV/AC = 50000/55000 ≈ 0.91. A CPI less than 1 indicates the project is over budget.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • CPI = 1.10; project is on budget

    Why it's wrong here

    Incorrect.

  • CPI = 1.09; project is under budget

    Why it's wrong here

    Incorrect calculation.

  • CPI = 0.83; project is over budget

    Why it's wrong here

    Incorrect calculation.

  • CPI = 0.91; project is over budget

    Why this is correct

    Correct: CPI < 1 means over budget.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.