PK0-005 Project Life Cycle Practice Question
A change request to add a new feature has been submitted. After impact analysis, the change control board (CCB) approves the change. What should the project manager do next?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Implement the change and update baselines
After approval, the project manager must implement the change, which includes updating all relevant baselines (scope, schedule, cost) and communicating the change to stakeholders.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Reject the change request
Why it's wrong here
The CCB has already approved it.
- ✗
Escalate to the sponsor
Why it's wrong here
The CCB has authority to approve; escalation is not necessary.
- ✓
Implement the change and update baselines
Why this is correct
Approved changes must be integrated into the project.
- ✗
Conduct another impact analysis
Why it's wrong here
Impact analysis is done before CCB approval.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.