PK0-005 Project Life Cycle Practice Question

A change request to add a new feature has been submitted. After impact analysis, the change control board (CCB) approves the change. What should the project manager do next?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Implement the change and update baselines

After approval, the project manager must implement the change, which includes updating all relevant baselines (scope, schedule, cost) and communicating the change to stakeholders.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Reject the change request

    Why it's wrong here

    The CCB has already approved it.

  • Escalate to the sponsor

    Why it's wrong here

    The CCB has authority to approve; escalation is not necessary.

  • Implement the change and update baselines

    Why this is correct

    Approved changes must be integrated into the project.

  • Conduct another impact analysis

    Why it's wrong here

    Impact analysis is done before CCB approval.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.