Courseiva
Project Management ConceptsmediumMultiple ChoiceObjective-mapped

PK0-005 Project Management Concepts Practice Question

A project has a Net Present Value (NPV) of -$5,000. What does this indicate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is not financially viable

A negative NPV means the project's costs exceed its benefits, indicating it is not financially viable.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is not financially viable

    Why this is correct

    A negative NPV suggests the project may not be worthwhile.

  • The project will generate a profit of $5,000

    Why it's wrong here

    Negative NPV indicates a loss.

  • The project should be accepted because NPV is positive

    Why it's wrong here

    NPV is negative, not positive.

  • The payback period is less than 5 years

    Why it's wrong here

    NPV does not directly indicate payback period.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.