PK0-005 Project Life Cycle Practice Question
A project manager is preparing a procurement document that asks vendors to provide a price for a specific product. Which type of document is this?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Request for quotation (RFQ)
A request for quotation (RFQ) is used to obtain a price for a specific item.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Request for quotation (RFQ)
Why this is correct
RFQ is used to request a price for a specific product.
- ✗
Request for proposal (RFP)
Why it's wrong here
RFP is for soliciting proposals, not just pricing.
- ✗
Request for information (RFI)
Why it's wrong here
RFI is for gathering information, not pricing.
- ✗
Statement of work (SOW)
Why it's wrong here
SOW describes the work to be performed, not a request for price.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.