Question 203 of 500
Project Management ConceptsmediumMultiple ChoiceObjective-mapped

Quick Answer

The correct first step is to obtain approval for a project charter. This is essential because, according to PMI standards, a project charter formally authorizes the project, grants the project manager the authority to apply organizational resources, and establishes a direct link to strategic objectives. Without it, the project lacks official sanction and clear direction, making any subsequent planning or execution invalid. On the CompTIA Project+ PK0-005 exam, this scenario tests your understanding of the Initiating process group and the critical role of the charter in governance. A common trap is to jump into creating a schedule or assigning tasks, but the charter must come first to legitimize the work. Remember the memory tip: "No charter, no authority"—always secure the signed document before taking any other action.

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is assigned to a project that has already started without a formal project charter. What should the project manager do first?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Obtain approval for a project charter

Without a formal project charter, the project lacks official authorization and a clear link to organizational objectives. The project manager must first obtain approval for a project charter to secure the authority to apply organizational resources and formally initiate the project, as defined by PMI standards.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Obtain approval for a project charter

    Why this is correct

    Charter is essential to authorize the project and assign the PM.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Create a work breakdown structure

    Why it's wrong here

    WBS should be done after the charter is in place.

  • Develop a project management plan

    Why it's wrong here

    The plan is created after the charter.

  • Identify stakeholders

    Why it's wrong here

    Stakeholder identification typically occurs after the charter.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Cisco often tests the misconception that planning activities like creating a WBS or management plan can proceed without formal authorization, but the exam emphasizes that the charter must be approved first to establish the project's legitimacy and the project manager's authority.

Detailed technical explanation

How to think about this question

The project charter formally authorizes the project and names the project manager, granting them the authority to use organizational resources. In practice, without a signed charter, the project manager has no official standing to request budget, assign team members, or make binding decisions, which can lead to scope creep and resource conflicts. PMBOK Guide emphasizes that the charter is the first deliverable in the Initiating process group.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A junior network technician can log in to a core router but cannot reach the enable prompt or configuration mode. The AAA server is authenticating the login — but the authorisation policy only grants privilege level 1, not 15. Authentication (who you are) is working; authorisation (what you can do) is not.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Obtain approval for a project charter — Without a formal project charter, the project lacks official authorization and a clear link to organizational objectives. The project manager must first obtain approval for a project charter to secure the authority to apply organizational resources and formally initiate the project, as defined by PMI standards.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.