PK0-005 Project Management Concepts Practice Question
Which of the following is NOT a typical constraint in the triple constraint of project management?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Quality
The classic triple constraint includes scope, cost, and schedule. Quality is often added as a fourth constraint.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Cost
Why it's wrong here
Cost is a constraint.
- ✗
Schedule
Why it's wrong here
Schedule is a constraint.
- ✓
Quality
Why this is correct
Quality is often an additional constraint, not part of the original triple.
- ✗
Scope
Why it's wrong here
Scope is a constraint.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.