PK0-005 Practice Question: In a risk register, the risk score is typically…

In a risk register, the risk score is typically calculated by multiplying which two fields?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Probability and impact

Risk score is usually probability multiplied by impact.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Impact and urgency

    Why it's wrong here

    Risk score multiplies probability by impact, not impact by urgency. Urgency belongs to incident prioritisation matrices, where it pairs with impact to set response times. It is tempting because urgency and impact both sound like severity measures, but a risk register's score uses likelihood of occurrence, not how soon action is needed.

  • ✓

    Probability and impact

    Why this is correct

    Risk scoring multiplies the likelihood (probability) of the risk occurring by the severity of its consequence (impact), producing a numeric exposure value that drives prioritisation in the register. These two fields form the standard qualitative risk calculation.

  • ✗

    Risk score and residual risk

    Why it's wrong here

    Risk score and residual risk are both outputs of the assessment, not inputs to the multiplication. It is tempting because residual risk is a recognised register field, useful after mitigation to show remaining exposure, but the score itself derives from probability and impact before any controls are applied.

  • ✗

    Probability and risk trigger

    Why it's wrong here

    A risk trigger is an event indicator that signals a risk is occurring, not a numeric multiplier. It is tempting because triggers are recorded in registers to prompt action, which is useful for monitoring, but the score multiplies probability by impact, both of which are rated numerically.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.