mediumMultiple Choice

PK0-005 Practice Question: Refer to the exhibit

Exhibit

Project Risk Register (Excerpt)

Risk ID | Risk Description | Probability | Impact | Risk Score | Response
R1 | Supplier delay | 0.4 | 0.3 | 0.12 | Transfer
R2 | Staff turnover | 0.6 | 0.5 | 0.30 | Mitigate
R3 | Scope creep | 0.5 | 0.4 | 0.20 | Accept
R4 | Technical failure | 0.3 | 0.7 | 0.21 | Avoid

Refer to the exhibit. Based on the risk register, which risk should receive the highest priority for response?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

R2

The risk with the highest risk score (0.30) is R2 (Staff turnover). Risk score is typically used to prioritize risks for response planning.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    R4

    Why it's wrong here

    R4 has a risk score of 0.21.

  • ✗

    R1

    Why it's wrong here

    R1 has a risk score of 0.12, which is the lowest.

  • ✓

    R2

    Why this is correct

    R2 has the highest risk score of 0.30.

  • ✗

    R3

    Why it's wrong here

    R3 has a risk score of 0.20.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.