PK0-005 Project Life Cycle Practice Question
During project closing, a project manager must complete several activities. Which TWO are appropriate for project closure?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Archive project documents
Project closure includes formal acceptance from the sponsor/customer and archiving project documents. Releasing resources and lessons learned are also closure activities, but the question asks for TWO from the options.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Create the project charter
Why it's wrong here
The charter is created during initiating, not closing.
- ✗
Update the risk register
Why it's wrong here
Risk register updates occur throughout the project, but closure focuses on finality.
- ✓
Archive project documents
Why this is correct
Correct. Archiving documents is part of closing.
- ✗
Develop the project schedule
Why it's wrong here
The schedule is developed during planning.
- ✓
Obtain formal acceptance of deliverables from the sponsor
Why this is correct
Correct. Formal acceptance is a key closure activity.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.