Courseiva
Project Life CycleeasyMultiple SelectObjective-mapped

PK0-005 Project Life Cycle Practice Question

During project closing, a project manager must complete several activities. Which TWO are appropriate for project closure?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Archive project documents

Project closure includes formal acceptance from the sponsor/customer and archiving project documents. Releasing resources and lessons learned are also closure activities, but the question asks for TWO from the options.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Create the project charter

    Why it's wrong here

    The charter is created during initiating, not closing.

  • Update the risk register

    Why it's wrong here

    Risk register updates occur throughout the project, but closure focuses on finality.

  • Archive project documents

    Why this is correct

    Correct. Archiving documents is part of closing.

  • Develop the project schedule

    Why it's wrong here

    The schedule is developed during planning.

  • Obtain formal acceptance of deliverables from the sponsor

    Why this is correct

    Correct. Formal acceptance is a key closure activity.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.