Courseiva
Project Life Cycle →mediumMultiple Choice

PK0-005 Project Life Cycle Practice Question

In earned value management, the project has an EV of $50,000, PV of $60,000, and AC of $55,000. What is the cost variance (CV)?

⚠ Common exam trap

PK0-005 often tests formula confusion — candidates mix up CV (EV − AC) with SV (EV − PV), or drop the negative sign, producing the wrong answer.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

-$5,000

Cost Variance (CV) is calculated as EV − AC. With EV = $50,000 and AC = $55,000, CV = $50,000 − $55,000 = −$5,000, indicating the project is over budget by $5,000.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    -$10,000

    Why it's wrong here

    This value equals EV minus PV, the schedule variance, not the cost variance. It is tempting because the numbers are identical in magnitude to the correct CV, but CV requires subtracting AC from EV, giving negative $5,000.

  • ✗

    $10,000

    Why it's wrong here

    CV is EV minus AC, giving 50,000 minus 55,000, which is negative $5,000, not positive $10,000. The figure is tempting because it equals the schedule variance (EV minus PV), which measures timing rather than cost performance.

  • ✓

    -$5,000

    Why this is correct

    Cost variance is EV minus AC: $50,000 − $55,000 = −$5,000. The negative result satisfies the stem's requirement to quantify cost performance, showing the project has overspent by $5,000 against the work completed. PV is irrelevant here, since CV measures actual cost efficiency, not schedule.

  • ✗

    $5,000

    Why it's wrong here

    A $5,000 figure is the schedule variance (EV − PV = −$10,000 is wrong; SV is actually −$10,000, so $5,000 matches nothing here), whereas cost variance requires EV − AC = $50,000 − $55,000 = −$5,000. The positive sign is tempting because AC exceeds EV by exactly $5,000, but CV must be negative when overspent.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.