Courseiva
hardMultiple Select

PK0-005 Practice Question: Which THREE components are typically included in…

Which THREE components are typically included in a project management plan?

⚠ Common exam trap

CompTIA often tests the distinction between 'project management plan components' (which include baselines and subsidiary plans) and 'project documents' (like issue logs and stakeholder registers), so candidates mistakenly include operational logs or registers as part of the formal plan.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Schedule baseline

The project management plan is the formal, approved document that defines how the project is executed, monitored, and controlled. The schedule baseline (B), cost baseline (D), and scope baseline (E) are three of the key baselines that collectively form the performance measurement baseline (PMB) against which project performance is measured. These baselines are formally approved and can only be changed through a formal change control process.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Issue log

    Why it's wrong here

    An issue log is a project execution artefact that records problems as they arise, not a component defined within the project management plan itself. It would be the correct choice when documenting and tracking active issues during monitoring and controlling processes.

  • ✓

    Schedule baseline

    Why this is correct

    The schedule baseline is the approved version of the schedule, used to compare actual progress against planned dates. It is one of the three baselines integrated into the project management plan, directly satisfying the stem's requirement for a typical plan component.

  • ✗

    Stakeholder register

    Why it's wrong here

    The stakeholder register is a separate project document identifying people and their interests; it informs the plan but is not a component within it. It would be the correct choice when identifying and analysing stakeholders during project initiation.

  • ✓

    Cost baseline

    Why this is correct

    The cost baseline is the time-phased approved budget against which project spending is tracked and variances measured. It forms part of the project management plan's baseline trio, satisfying the stem's requirement for a plan component rather than a subsidiary document such as the cost management plan.

  • ✓

    Scope baseline

    Why this is correct

    The scope baseline comprises the approved scope statement, WBS and WBS dictionary, providing the reference for scope verification and change control. It is one of the three baselines contained within the project management plan, matching the stem's requirement for a plan component.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.