PK0-005 Project Management Concepts Practice Question
A project manager is leading a software development project with stable requirements and a fixed budget. The team prefers a sequential approach with clear phases. Which methodology is most appropriate?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Predictive (Waterfall)
Predictive (waterfall) works well when requirements are stable and a sequential approach is preferred.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Predictive (Waterfall)
Why this is correct
Best for stable requirements and sequential phases.
- ✗
Scrum
Why it's wrong here
Scrum is an agile framework.
- ✗
Hybrid
Why it's wrong here
Hybrid combines elements but may not be necessary here.
- ✗
Agile
Why it's wrong here
Agile is iterative and better for evolving requirements.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.