Courseiva
Project Management Concepts →mediumMultiple Choice

PK0-005 Project Management Concepts Practice Question

A project manager is leading a software development project with stable requirements and a fixed budget. The team prefers a sequential approach with clear phases. Which methodology is most appropriate?

⚠ Common exam trap

PK0-005 often tests the misconception that Agile/Scrum is always 'better' — candidates must recognize that stable requirements and fixed budgets favor Predictive/Waterfall, not iterative frameworks.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Predictive (Waterfall)

Predictive (Waterfall) is the correct methodology because it is designed for projects with stable, well-understood requirements, a fixed budget, and a preference for sequential phases with clear gates. Waterfall's linear structure — requirements, design, build, test, deploy — matches the team's desire for defined phases and works well when scope is unlikely to change. Scrum, Agile, and Hybrid all introduce iterative cycles and embrace changing requirements, which is unnecessary and potentially disruptive when requirements are already stable.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Predictive (Waterfall)

    Why this is correct

    Predictive methodology plans the full scope upfront and executes sequential phases, suiting stable requirements and a fixed budget. Waterfall's linear structure matches the team's stated preference for clear phases, satisfying the stem's constraint of unchanging requirements.

  • ✗

    Scrum

    Why it's wrong here

    Scrum structures delivery into timeboxed sprints with a backlog that accommodates changing requirements, which contradicts the stable requirements and fixed budget here. It would be correct where scope is emergent and iterative inspection and adaptation are needed.

  • ✗

    Hybrid

    Why it's wrong here

    Hybrid blends sequential planning with iterative delivery, adding Agile ceremonies and feedback loops the stable, fixed-budget project does not need. It would be correct where some components have uncertain requirements while others follow a defined plan.

  • ✗

    Agile

    Why it's wrong here

    Agile delivers work in short iterative increments with evolving scope, which conflicts with the fixed budget and stable requirements described. It would be the right choice where requirements are uncertain and frequent stakeholder feedback drives reprioritisation across sprints.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.