Courseiva

PK0-005 Project Management Concepts Practice Question

A company is evaluating two projects. Project A has an NPV of $50,000 and a payback period of 3 years. Project B has an NPV of $40,000 and a payback period of 2 years. Which project should be selected based on NPV?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project A because it has a higher NPV

NPV is a primary indicator of profitability. Higher NPV is better, regardless of payback period.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Neither project should be selected

    Why it's wrong here

    NPV is the stated selection criterion, and Project A's $50,000 exceeds Project B's $40,000, so a positive-NPV option exists. Rejecting both is tempting when payback periods dominate thinking, but payback is a secondary liquidity measure; it would be correct only if both projects had negative NPV.

  • ✗

    Project B because it has a shorter payback period

    Why it's wrong here

    Payback period measures how quickly outlay is recovered and ignores cash flows after that point, so it cannot rank projects by net present value. It is tempting because shorter recovery feels safer. NPV is the stated criterion, and Project A's higher NPV of $50,000 makes it the selection.

  • ✗

    Both projects are equally good

    Why it's wrong here

    The NPVs differ by $10,000, so the projects are not equivalent on the stated criterion. Equal ranking is tempting when both NPVs are positive and both payback periods are short, but NPV is an absolute dollar measure; it would apply only if the two NPV figures were identical.

  • ✓

    Project A because it has a higher NPV

    Why this is correct

    Project A delivers the greater net present value, $50,000 against $40,000, so it adds more value once future cash flows are discounted to present terms. The stem explicitly asks for selection based on NPV, making payback period irrelevant here despite Project B's faster two-year recovery.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.