During project execution, a key stakeholder requests a change that would require additional funding. The project manager should:

⚠ Common exam trap

The PK0-005 exam often tests the misconception that the sponsor can unilaterally approve cost-related changes, but the correct answer requires recognizing that the change control board holds the authority for all formal change approvals, regardless of funding source.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Submit the change request to the change control board

In project management, any change that impacts the budget must follow the formal change control process. The project manager should submit the change request to the change control board (CCB) for evaluation and approval, as the CCB has the authority to approve or reject changes that affect cost, scope, or schedule. This ensures that all impacts are assessed and that the project remains aligned with its baseline.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Ask the sponsor for approval

    Why it's wrong here

    Escalating straight to the sponsor bypasses the change control process; the request must first be documented, assessed for impact, and reviewed by the change control board. Sponsor approval is correct for urgent changes exceeding the board's authority, but routine funding changes follow integrated change control first.

  • ✓

    Submit the change request to the change control board

    Why this is correct

    Routing the funding change through the change control board satisfies the stem's cost-impact constraint. The board holds the authority to approve or reject budget-affecting changes, so the project manager must not authorise additional funding unilaterally.

  • ✗

    Refuse the change because it increases cost

    Why it's wrong here

    Refusing outright ignores the change control process, which exists to evaluate requests on merit rather than cost alone. Rejection is valid only after assessment shows the change harms scope, schedule, or benefits. The project manager should document and route the request through the change control board.

  • ✗

    Implement the change immediately

    Why it's wrong here

    Implementing immediately skips impact analysis, approval, and baseline updates, causing uncontrolled scope and cost creep. Acting at once is appropriate only for emergency changes under a defined expedited process. Here the request must be documented and evaluated through integrated change control before any work proceeds.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.