A project team is using Agile methodology. The product owner frequently changes priorities during the sprint, causing confusion. What is the most appropriate action for the project manager (scrum master)?

⚠ Common exam trap

CompTIA often tests the misconception that the product owner can change priorities at any time, tempting candidates to choose 'allow changes as long as the team agrees' (Option D), but the correct Agile principle is to protect the sprint commitment by deferring changes to the next sprint.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Add the changes to the product backlog for the next sprint

In Agile (specifically Scrum), the sprint is a time-boxed period during which the team commits to a set of work. The product owner should not change priorities mid-sprint because it disrupts the team's focus and velocity. The correct action is to add the new priorities to the product backlog for consideration in the next sprint, preserving the integrity of the current sprint and the Scrum framework.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Immediately stop the sprint and reprioritize

    Why it's wrong here

    Stopping a sprint is drastic; typically only done for critical issues.

  • Ask the product owner to be less involved

    Why it's wrong here

    Product owner involvement is essential; the issue is about process, not involvement.

  • Add the changes to the product backlog for the next sprint

    Why this is correct

    Changes should be placed in the product backlog and considered for future sprints.

  • Allow changes as long as the team agrees

    Why it's wrong here

    Changes during a sprint disrupt team focus and should be avoided unless critical.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.