During project initiation, the project sponsor provides the project manager with a document that authorizes the project and assigns the project manager. This document also outlines high-level scope, budget, and timeline. Which document is this?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project charter

The project charter is the formal authorization document that gives the PM authority and outlines high-level constraints.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project charter

    Why this is correct

    The charter authorizes the project and the PM.

  • Project management plan

    Why it's wrong here

    The plan is developed after initiation and contains detailed plans.

  • Scope statement

    Why it's wrong here

    The scope statement is part of planning, detailing scope.

  • Business case

    Why it's wrong here

    The business case justifies the project but does not authorize it.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.