Tools and Documentation →hardMultiple Choice

PK0-005 Tools and Documentation Practice Question

A project manager is creating a risk register. One risk has a probability of 0.3 and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

$15,000

EMV = Probability * Impact = 0.3 * $50,000 = $15,000.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    $1,500

    Why it's wrong here

    $1,500 misplaces the decimal by a factor of ten; 0.3 × $50,000 equals $15,000. It is tempting because it looks like a correctly scaled small result, and it would be correct if the impact were $5,000 rather than $50,000.

  • ✓

    $15,000

    Why this is correct

    Multiplying probability by impact gives the expected monetary value: 0.3 × $50,000 = $15,000. This quantifies the risk's average financial exposure, satisfying the register's requirement to express each risk in monetary terms for comparison and contingency budgeting.

  • ✗

    $150,000

    Why it's wrong here

    Multiplying probability by impact gives $15,000, not $150,000; this figure results from dividing impact by probability or misplacing the decimal. It is tempting because it is the largest number offered, and it would be correct if the probability were 3.0, which is impossible since probability cannot exceed 1.

  • ✗

    $50,000

    Why it's wrong here

    $50,000 is the raw impact, ignoring the 0.3 probability entirely. It is tempting because impact is the headline figure in a risk register, and it would be correct if the question asked for the monetary loss should the risk occur with certainty.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.