PK0-005 Project Life Cycle Practice Question
A project manager is developing a communication plan. Which two elements should be included in the plan? (Select TWO)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Frequency of communication
A communication plan should include stakeholder communication needs and frequency, as well as the method of communication.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Frequency of communication
Why this is correct
Frequency is a key component.
- ✗
Risk register
Why it's wrong here
The risk register is a separate document.
- ✗
Project charter
Why it's wrong here
Charter is created earlier.
- ✓
Stakeholder communication needs
Why this is correct
Essential for planning communications.
- ✗
Work breakdown structure
Why it's wrong here
WBS is for scope management.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.