Courseiva
Project Life Cycle →mediumMultiple Select

PK0-005 Project Life Cycle Practice Question

A project manager is developing a communication plan. Which two elements should be included in the plan? (Select TWO)

⚠ Common exam trap

PK0-005 often mixes inputs (charter, risk register, WBS) with plan components — candidates must distinguish documents that FEED the plan from elements that BELONG in the plan.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Frequency of communication

Option A (Frequency of communication) is correct because a communication plan must specify how often information is distributed—daily, weekly, monthly, or at milestones—so stakeholders know when to expect updates and the team can schedule reporting activities. Option D (Stakeholder communication needs) is correct because the plan must identify who needs what information, in what format, and through which channel, tailoring communications to each stakeholder's requirements and influence. Options B, C, and E are incorrect because the risk register, project charter, and work breakdown structure are project artifacts or inputs that inform planning, not elements that constitute the communication plan itself.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Frequency of communication

    Why this is correct

    Frequency of communication specifies how often each stakeholder group receives information, satisfying the plan's need to schedule interactions. It complements details such as method, sender, and audience, ensuring stakeholders know when to expect updates rather than only what will be communicated.

  • ✗

    Risk register

    Why it's wrong here

    The risk register records identified risks and responses; it is an input to communication planning, not a component of the plan. It tempts because risk reporting is a communication activity, but the plan itself defines audiences, message formats, timing, channels and responsible senders.

  • ✗

    Project charter

    Why it's wrong here

    The project charter authorises the project and defines objectives; it is an input to communication planning, not a component of the plan. It tempts because charter stakeholders shape who receives information, but the plan itself specifies audiences, methods, timing and responsibilities.

  • ✓

    Stakeholder communication needs

    Why this is correct

    Stakeholder communication needs define what each audience must receive, when, and in what format, directly shaping the plan's content and cadence. Without mapping these requirements, the plan cannot satisfy the project's information-distribution constraint or tailor messaging to differing stakeholder expectations.

  • ✗

    Work breakdown structure

    Why it's wrong here

    The work breakdown structure decomposes deliverables and is an input for identifying who needs which information, not a communication plan element. It tempts because WBS components often map to reporting groups, but the plan documents stakeholders, message content, frequency, channels and owners.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.