Courseiva
Project Life CyclemediumMultiple SelectObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project manager is developing a communication plan. Which two elements should be included in the plan? (Select TWO)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Frequency of communication

A communication plan should include stakeholder communication needs and frequency, as well as the method of communication.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Frequency of communication

    Why this is correct

    Frequency is a key component.

  • Risk register

    Why it's wrong here

    The risk register is a separate document.

  • Project charter

    Why it's wrong here

    Charter is created earlier.

  • Stakeholder communication needs

    Why this is correct

    Essential for planning communications.

  • Work breakdown structure

    Why it's wrong here

    WBS is for scope management.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.