Question 135 of 500
Project Life Cycle PhaseshardMultiple ChoiceObjective-mapped

Quick Answer

The correct interpretation is that the project is over budget and ahead of schedule. This is determined by the earned value interpretation: a cost performance index (CPI) of 0.8, being less than 1.0, means the project is earning only 80 cents of value for every dollar spent, indicating a cost overrun; conversely, a schedule performance index (SPI) of 1.2, being greater than 1.0, means the project is completing 20% more work than planned, placing it ahead of schedule. On the CompTIA Project+ PK0-005 exam, this question tests your ability to apply earned value management (EVM) metrics during the monitoring and controlling phase, where a common trap is confusing the direction of the indices—remember that below 1 is bad for both cost and schedule, but here they move in opposite directions. A useful memory tip is to think of CPI as the "cost penalty" (lower is worse) and SPI as the "speed prize" (higher is better), so CPI < 1 hurts the budget while SPI > 1 helps the timeline.

PK0-005 Project Life Cycle Phases Practice Question

This PK0-005 practice question tests your understanding of project life cycle phases. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project is in the monitoring and controlling phase. The project manager notices that the cost performance index (CPI) is 0.8 and the schedule performance index (SPI) is 1.2. What does this indicate about the project?

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is over budget and ahead of schedule

Option D is correct because CPI < 1 means the project is over budget, and SPI > 1 means it is ahead of schedule. Option A is incorrect because it states under budget. Option B is incorrect because it states behind schedule. Option C is incorrect because it states both on track.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is over budget and ahead of schedule

    Why this is correct

    CPI<1 over budget, SPI>1 ahead of schedule.

    Related concept

    Read the scenario before looking for a memorised answer.

  • The project is on budget and on schedule

    Why it's wrong here

    CPI and SPI not equal to 1.

  • The project is under budget and ahead of schedule

    Why it's wrong here

    CPI <1 indicates over budget.

  • The project is over budget and behind schedule

    Why it's wrong here

    SPI >1 indicates ahead of schedule.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PK0-005 exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Life Cycle Phases — This question tests Project Life Cycle Phases — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: The project is over budget and ahead of schedule — Option D is correct because CPI < 1 means the project is over budget, and SPI > 1 means it is ahead of schedule. Option A is incorrect because it states under budget. Option B is incorrect because it states behind schedule. Option C is incorrect because it states both on track.

What should I do if I get this PK0-005 question wrong?

Identify which PK0-005 exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on PK0-005

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. While monitoring and controlling, the project manager reviews earned value metrics and finds CPI = 0.8 and SPI = 1.1. What does this indicate?

medium
  • A.Over budget but ahead of schedule
  • B.Under budget and ahead of schedule
  • C.Under budget but behind schedule
  • D.Over budget and behind schedule

Why A: CPI less than 1 indicates over budget; SPI greater than 1 indicates ahead of schedule. Therefore the project is over budget but ahead of schedule.

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.