A project manager needs to assign tasks to team members. Which document provides the detailed breakdown of work packages?
⚠ Common exam trap
Many exam-takers confuse the project schedule (which shows timing) with the WBS (which shows the breakdown of work), leading them to select the schedule when the question specifically asks for the document that provides the detailed breakdown of work packages.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Work breakdown structure
The Work Breakdown Structure (WBS) is the correct document because it provides a hierarchical decomposition of the total scope of work into manageable work packages. Each work package represents a deliverable or task that can be assigned, estimated, and tracked, making it the definitive source for task assignment details.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project schedule
Why it's wrong here
The schedule sequences activities against dates and dependencies; it does not decompose deliverables into work packages. It is tempting because it shows who does what and when, but that assignment derives from the work breakdown structure, which the schedule merely references.
- ✗
Project charter
Why it's wrong here
The charter authorises the project and names the sponsor and high-level objectives; it contains no work-package decomposition. It is tempting because it is the founding document, but task assignment requires the work breakdown structure, which decomposes deliverables into assignable packages.
- ✓
Work breakdown structure
Why this is correct
The work breakdown structure decomposes project scope into work packages, the lowest deliverable level, from which tasks are assigned. It provides the hierarchical detail needed to allocate responsibilities, satisfying the stem's requirement for a work-package breakdown.
- ✗
Risk register
Why it's wrong here
The risk register catalogues identified threats with probability, impact and response owners; it holds no work-package detail. It is tempting because it lists owners, but those are risk-response owners, not task assignees, so it cannot supply the breakdown needed for assigning work.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.