Courseiva
hardMultiple Choice

PK0-005 Practice Question: A project has earned value (EV) of $50,000,…

A project has earned value (EV) of $50,000, actual cost (AC) of $60,000, and planned value (PV) of $55,000. What is the cost performance index (CPI)?

⚠ Common exam trap

Candidates often confuse CPI with SPI (schedule performance index), leading candidates to mistakenly divide EV by PV instead of EV by AC, which yields option A (0.91).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

0.83

The cost performance index (CPI) is calculated as EV divided by AC. With EV = $50,000 and AC = $60,000, CPI = 50,000 / 60,000 = 0.8333, which rounds to 0.83. A CPI less than 1.0 indicates the project is over budget, as each dollar of work completed costs more than planned.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    0.91

    Why it's wrong here

    CPI is EV divided by AC, so $50,000 ÷ $60,000 = 0.83, not 0.91. The figure 0.91 is tempting because it resembles the result of dividing EV by PV ($50,000 ÷ $55,000 = 0.91), which is the schedule performance index, not the cost performance index.

  • ✗

    1.20

    Why it's wrong here

    CPI is EV divided by AC, giving $50,000 ÷ $60,000 = 0.83, not 1.20. The value 1.20 is tempting because it is AC divided by EV ($60,000 ÷ $50,000), the inverse ratio, which would only be used to derive the estimate at completion via the bottom-up formula.

  • ✓

    0.83

    Why this is correct

    CPI is earned value divided by actual cost: $50,000 / $60,000 = 0.83. A value below 1.0 indicates the project is over budget, since each dollar spent has delivered only 83 cents of earned value.

  • ✗

    1.10

    Why it's wrong here

    CPI is EV divided by AC, giving $50,000 ÷ $60,000 = 0.83, not 1.10. The value 1.10 is tempting because it is PV divided by EV ($55,000 ÷ $50,000), a ratio describing planned versus earned value, which is not the cost performance index.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.