PK0-005 Project Life Cycle Practice Question
During project execution, a team member identifies a potential risk that was not included in the risk register. The project manager logs it and begins the risk assessment process. Where should this risk be recorded?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Risk register
Newly identified risks are added to the risk register for assessment and response planning.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Risk register
Why this is correct
The risk register documents all identified risks and their analysis.
- ✗
Issue log
Why it's wrong here
An issue is an event that has occurred; this is a potential risk.
- ✗
Change request log
Why it's wrong here
Change requests are for changes to scope, schedule, etc.
- ✗
Lessons learned
Why it's wrong here
Lessons learned capture knowledge after the fact.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.