Courseiva
Project Life CyclehardMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

During project execution, a team member identifies a potential risk that was not included in the risk register. The project manager logs it and begins the risk assessment process. Where should this risk be recorded?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Risk register

Newly identified risks are added to the risk register for assessment and response planning.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Risk register

    Why this is correct

    The risk register documents all identified risks and their analysis.

  • Issue log

    Why it's wrong here

    An issue is an event that has occurred; this is a potential risk.

  • Change request log

    Why it's wrong here

    Change requests are for changes to scope, schedule, etc.

  • Lessons learned

    Why it's wrong here

    Lessons learned capture knowledge after the fact.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.