Project Management ConceptsmediumMultiple ChoiceObjective-mapped

PK0-005 Project Management Concepts Practice Question

A project to build a website is expected to take 6 months with a fixed budget. During planning, the team determines that the requirements are well-understood and unlikely to change. Which methodology is most appropriate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Predictive

Predictive (waterfall) methodology works best when requirements are clear and stable. It uses sequential phases and fixed scope.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Kanban

    Why it's wrong here

    Kanban is an agile method focusing on continuous delivery.

  • Predictive

    Why this is correct

    Correct. Predictive is suitable for stable requirements.

  • Agile

    Why it's wrong here

    Agile is better for evolving requirements.

  • Scrum

    Why it's wrong here

    Scrum is an agile framework for iterative development.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.