PK0-005 Practice Question: A project to deploy a new CRM system is in the…

A project to deploy a new CRM system is in the execution phase. The team frequently encounters integration issues because the development environment does not match the production environment. The project manager has not enforced change control, and team members have made undocumented changes to the development environment. What should the project manager do first?

⚠ Common exam trap

A common mix-up: candidates choose Option B (halt all development) because it seems decisive, but the PMI and CompTIA PK0-005 emphasize first addressing the process failure (change control) before taking disruptive actions, as halting without assessment wastes time and does not resolve the underlying issue.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Implement a formal change control process and assess the impact of previous undocumented changes.

The immediate priority is to establish a formal change control process to prevent further undocumented changes, which are the root cause of the environment drift. The project manager must then assess the impact of previous undocumented changes to understand what modifications were made, how they affect integration, and what steps are needed to align the development and production environments. This approach addresses the process failure first, enabling controlled remediation rather than continuing with a broken process or halting work without a plan.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Continue development and document issues for post-implementation review.

    Why it's wrong here

    Continuing without addressing the root cause will likely lead to more integration problems.

  • Immediately halt all development until environments are aligned.

    Why it's wrong here

    Halting all development is too drastic; alignment can proceed while managing changes.

  • Implement a formal change control process and assess the impact of previous undocumented changes.

    Why this is correct

    Establishing change control helps prevent future undocumented changes and allows assessment of current issues.

  • Reassign developers to fix integration issues without changing the process.

    Why it's wrong here

    Reassigning resources does not prevent recurrence; change control is needed.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.