mediumMultiple ChoiceObjective-mapped
PK0-005 Practice Question: A construction project is nearing the end of the…
A construction project is nearing the end of the executing phase. The project manager is preparing for the closure phase. During a review, the project manager discovers that two deliverables have not been formally accepted by the client due to minor quality issues. The team has already started demobilizing resources. What should the project manager do to properly close the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Correct the quality issues and obtain sign-off from the client before closing.
The correct action is to resolve the quality issues and obtain formal acceptance before proceeding to closure. Option A is correct because all deliverables must be formally accepted by the client to close the project or phase. Option B is wrong because closing without acceptance can lead to legal and financial liability. Option C is wrong because administrative closure requires that all deliverables are accepted. Option D is wrong because transferring deliverables with noted issues does not constitute acceptance and may result in rejection.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Correct the quality issues and obtain sign-off from the client before closing.
Why this is correct
Ensures deliverables meet acceptance criteria.
- ✗
Close the project and rely on the warranty period to fix issues later.
Why it's wrong here
Warranty is not a substitute for formal acceptance.
- ✗
Proceed with administrative closure and archive all project documents.
Why it's wrong here
Should not close without accepted deliverables.
- ✗
Transfer the deliverables to the client with a note that minor issues remain.
Why it's wrong here
Deliverables must be complete and accepted.
Visual reference
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.