- A
Correct the quality issues and obtain sign-off from the client before closing.
Ensures deliverables meet acceptance criteria.
- B
Close the project and rely on the warranty period to fix issues later.
Why wrong: Warranty is not a substitute for formal acceptance.
- C
Proceed with administrative closure and archive all project documents.
Why wrong: Should not close without accepted deliverables.
- D
Transfer the deliverables to the client with a note that minor issues remain.
Why wrong: Deliverables must be complete and accepted.
Quick Answer
The correct answer is to correct the quality issues and obtain sign-off from the client before closing. This is because formal acceptance of all deliverables is a mandatory prerequisite for phase or project closure under the CompTIA Project+ framework; closing a project with unaccepted deliverables violates the core principle of validated scope and exposes the organization to legal and financial liability. On the PK0-005 exam, this scenario tests your understanding of the closure process group and the trap of prioritizing resource demobilization over deliverable acceptance—a common mistake where test-takers choose to close prematurely. A key memory tip is "No sign-off, no close-off": never finalize a project until every deliverable has been formally accepted, regardless of team pressure or minor quality issues.
PK0-005 Project Life Cycle Phases Practice Question
This PK0-005 practice question tests your understanding of project life cycle phases. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A construction project is nearing the end of the executing phase. The project manager is preparing for the closure phase. During a review, the project manager discovers that two deliverables have not been formally accepted by the client due to minor quality issues. The team has already started demobilizing resources. What should the project manager do to properly close the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Correct the quality issues and obtain sign-off from the client before closing.
The correct action is to resolve the quality issues and obtain formal acceptance before proceeding to closure. Option B is correct because deliverables must be accepted to close the phase/project. Option A is wrong because closing without acceptance risks legal and financial liability. Option C is wrong as it bypasses the acceptance process. Option D is wrong because it ignores the client's requirements and may lead to rejection.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Correct the quality issues and obtain sign-off from the client before closing.
Why this is correct
Ensures deliverables meet acceptance criteria.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Close the project and rely on the warranty period to fix issues later.
Why it's wrong here
Warranty is not a substitute for formal acceptance.
- ✗
Proceed with administrative closure and archive all project documents.
Why it's wrong here
Should not close without accepted deliverables.
- ✗
Transfer the deliverables to the client with a note that minor issues remain.
Why it's wrong here
Deliverables must be complete and accepted.
Common exam traps
Common exam trap: answer the scenario, not the keyword
Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.
Detailed technical explanation
How to think about this question
This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
- Use explanations to understand the rule behind the answer.
TExam Day Tips
- Underline the problem statement mentally.
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which PK0-005 exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
- →
Project Life Cycle Phases — study guide chapter
Learn the concepts, then practise the questions
- →
Project Life Cycle Phases practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Life Cycle Phases — This question tests Project Life Cycle Phases — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Correct the quality issues and obtain sign-off from the client before closing. — The correct action is to resolve the quality issues and obtain formal acceptance before proceeding to closure. Option B is correct because deliverables must be accepted to close the phase/project. Option A is wrong because closing without acceptance risks legal and financial liability. Option C is wrong as it bypasses the acceptance process. Option D is wrong because it ignores the client's requirements and may lead to rejection.
What should I do if I get this PK0-005 question wrong?
Identify which PK0-005 exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 24, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.