Courseiva

PK0-005 Practice Question: Basics of IT Infrastructure and IT Project Management

A project manager is leading a project to upgrade the storage area network (SAN) for a hospital's electronic health records (EHR) system. The current SAN is reaching capacity and has performance issues during peak hours. The new SAN must support high availability with synchronous replication between two data centers located 10 km apart. The project budget is tight, and the timeline is aggressive. During a risk assessment, the project manager identifies that the fiber optic cable between the data centers is owned by a third-party provider and has a history of outages. The project sponsor is concerned about meeting the go-live date and asks the project manager to recommend a course of action to mitigate the risk of cable outages affecting the SAN replication. Which of the following is the BEST course of action?

⚠ Common exam trap

Candidates often confuse high-availability components (like redundant controllers) with network path redundancy, or incorrectly assume that adjusting replication timing or mode can substitute for fixing the underlying physical connectivity risk.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Work with the fiber provider to install a second, diverse fiber path between the data centers

The risk is specifically a single point of failure in the fiber path between data centers. Installing a second, diverse fiber path eliminates this single point of failure, ensuring synchronous replication can continue even if one cable is cut. This directly addresses the sponsor's concern about go-live delays due to cable outages, without changing the replication mode or adding unnecessary hardware.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Purchase redundant SAN controllers to provide failover in case of a controller failure

    Why it's wrong here

    Redundant controllers address hardware failure within the SAN, not the network link between sites.

  • Increase the synchronous replication interval to reduce the impact of potential outages

    Why it's wrong here

    Increasing the interval does not prevent outages and may lead to data loss if the link fails during replication.

  • Work with the fiber provider to install a second, diverse fiber path between the data centers

    Why this is correct

    A diverse path provides redundancy; if one cable fails, replication continues over the other, maintaining high availability.

  • Replace synchronous replication with asynchronous replication over the existing WAN connection

    Why it's wrong here

    Asynchronous replication introduces latency and potential data loss, and relies on the same network link.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.