PK0-005 Tools and Documentation Practice Question
A project manager is using a control chart to monitor quality. The data points fall within the control limits but show a run of seven points above the mean. What does this indicate?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Special cause variation is present
A run of seven or more points on one side of the mean is a rule for identifying special cause variation, even if within control limits.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The control limits need adjustment
Why it's wrong here
Control limits are based on process data; a run does not necessarily mean limits need adjustment.
- ✗
Common cause variation only
Why it's wrong here
A run of seven points suggests a non-random pattern, indicating special cause.
- ✓
Special cause variation is present
Why this is correct
Correct. The rule of seven indicates special cause variation.
- ✗
The process is out of control
Why it's wrong here
While not out of control in terms of limits, the run indicates special cause variation that needs investigation.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.