mediumMultiple Choice

PK0-005 Practice Question: During the planning phase, a team member…

During the planning phase, a team member estimates a task duration as 5-7 days based on a similar past project. Which estimating technique is being used?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Analogous estimating

Analogous estimating uses historical data from similar projects. Parametric uses statistical relationship, three-point uses optimistic/pessimistic/most likely, and bottom-up aggregates detailed estimates.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Parametric estimating

    Why it's wrong here

    Parametric estimating multiplies a unit rate by a quantity, such as cost per square metre; here the estimator used historical analogy from a comparable past project, which is analogous estimating. It is tempting because both draw on historical data, but parametric requires a measurable unit-rate relationship, not a single comparable case.

  • ✗

    Bottom-up estimating

    Why it's wrong here

    Bottom-up estimating aggregates estimates from the lowest-level work packages into a total; this estimate came from one analogous past project, not from decomposed components. It is tempting because both produce duration figures, but bottom-up requires the WBS and individual component estimates first.

  • ✓

    Analogous estimating

    Why this is correct

    Analogous estimating uses historical duration data from a comparable past project to derive the current estimate. The 5-7 day range drawn from a similar project directly matches this top-down, expert-judgement technique rather than parametric or three-point estimating.

  • ✗

    Three-point estimating

    Why it's wrong here

    Three-point estimating averages optimistic, most likely and pessimistic values, typically via PERT; here only a single range from one similar past project was used, which is analogous estimating. It is tempting because a range appears, but three-point requires three distinct estimates, not a borrowed historical span.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.