hardMultiple SelectObjective-mapped
PK0-005 Practice Question: A project manager is preparing for the project…
A project manager is preparing for the project closure phase. Which three activities should the project manager perform? (Select THREE).
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Release project resources
Closure activities include obtaining formal acceptance, documenting lessons learned, and releasing resources. Updating the stakeholder register is not a primary closure activity, and the charter is created earlier.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Update the stakeholder register
Why it's wrong here
Updating the stakeholder register is an ongoing process, not specific to closure.
- ✗
Create the project charter
Why it's wrong here
Creating the project charter is an activity performed during the initiation phase, not the closure phase, so it does not satisfy the requirement to execute post-delivery administrative and contractual closure tasks. It is tempting because the charter formally authorises the project and its manager, which might seem like a foundational document needed at any stage; however, it would only be correct if the question asked about initiating a new project rather than closing an existing one.
- ✓
Release project resources
Why this is correct
Releasing resources (team members, equipment) is part of project closure.
- ✓
Obtain formal acceptance of deliverables
Why this is correct
Formal acceptance is a key closure activity to confirm deliverables meet requirements.
- ✓
Document lessons learned
Why this is correct
Lessons learned are captured during closure to improve future projects.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.