hardMultiple Select
PK0-005 Practice Question: A project manager is preparing for the project…
A project manager is preparing for the project closure phase. Which three activities should the project manager perform? (Select THREE).
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Release project resources
Closure activities include obtaining formal acceptance, documenting lessons learned, and releasing resources. Updating the stakeholder register is not a primary closure activity, and the charter is created earlier.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Update the stakeholder register
Why it's wrong here
Stakeholder register updates belong to ongoing engagement throughout the project, not closure. Closure requires finalising the project charter sign-off, obtaining formal acceptance of deliverables, and archiving project documents. Updating the register is correct during initiation and execution when stakeholders or their influence change.
- ✗
Create the project charter
Why it's wrong here
Creating the project charter is an activity performed during the initiation phase, not the closure phase, so it does not satisfy the requirement to execute post-delivery administrative and contractual closure tasks. It is tempting because the charter formally authorises the project and its manager, which might seem like a foundational document needed at any stage; however, it would only be correct if the question asked about initiating a new project rather than closing an existing one.
- ✓
Release project resources
Why this is correct
Releasing project resources satisfies the closure constraint by formally disbanding the team once deliverables are accepted. This frees personnel for other assignments and closes cost accounts, preventing further charges against the project budget. Unlike ongoing execution activities, resource release confirms the project has ended and no remaining work requires staffing.
- ✓
Obtain formal acceptance of deliverables
Why this is correct
Obtaining formal acceptance confirms stakeholders agree deliverables meet requirements, satisfying the closure prerequisite that sign-off precedes finalising the project. Without documented acceptance, the project cannot be formally closed or resources released, since unresolved disputes over scope would remain open.
- ✓
Document lessons learned
Why this is correct
Documenting lessons learned captures what succeeded and failed, feeding organisational process assets so future projects avoid repeated mistakes. It directly satisfies the closure-phase requirement to consolidate project knowledge before the team disbands and resources are released. This activity preserves tacit insight that would otherwise be lost once team members move to new assignments.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.