Courseiva
Project Life CyclemediumMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project manager is developing a network diagram for a software rollout. Activity D (3 days) can start only after Activity C (2 days) finishes, and Activity E (4 days) can start when Activity C starts. Activities D and E must both finish before Activity F (1 day) begins. What type of dependency exists between Activity C and Activity E?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Start-to-Start (SS)

Start-to-start (SS) means the successor activity can start when the predecessor starts. Activity E starts when Activity C starts, so it's SS.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Start-to-Start (SS)

    Why this is correct

    E can start when C starts, which matches SS.

  • Start-to-Finish (SF)

    Why it's wrong here

    SF is rare and would mean C starts after E finishes; incorrect.

  • Finish-to-Start (FS)

    Why it's wrong here

    FS would require C to finish before E starts, but E can start when C starts.

  • Finish-to-Finish (FF)

    Why it's wrong here

    FF would require both to finish together; not the case.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.