Tools and Documentation →mediumMultiple Choice

PK0-005 Tools and Documentation Practice Question

A project manager is creating a RACI matrix for the project. One activity involves conducting security testing. The security lead will perform the testing, the project manager is responsible for ensuring it happens, and the compliance officer needs to be informed of the results. Which assignment is correct?

⚠ Common exam trap

The trap is confusing the Responsible and Accountable roles, especially when the project manager is involved — candidates often assume the project manager is always Responsible, but they are typically Accountable for ensuring work is done.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Security lead: Responsible; Project manager: Accountable; Compliance officer: Informed

In a RACI matrix, the person who performs the work is Responsible (R), the person ultimately answerable for the correct completion is Accountable (A), and those who need to be kept informed are Informed (I). Here, the security lead performs the testing, so they are Responsible; the project manager ensures it happens and is ultimately answerable, so they are Accountable; the compliance officer needs to be informed, so they are Informed. This matches option C.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Security lead: Accountable; Project manager: Informed; Compliance officer: Responsible

    Why it's wrong here

    The security lead performs the testing, making them Responsible, not Accountable; the project manager ensuring it happens is Accountable, not Informed. This arrangement would fit a scenario where the compliance officer executes the testing and the security lead owns its outcome, which the stem does not describe.

  • ✗

    Security lead: Responsible; Project manager: Informed; Compliance officer: Accountable

    Why it's wrong here

    The compliance officer only needs informing of results, so Accountable contradicts the stem; the project manager ensures the work happens, which is Accountable rather than Informed. This mapping would suit a scenario where the compliance officer owns the testing outcome and the project manager merely receives updates.

  • ✓

    Security lead: Responsible; Project manager: Accountable; Compliance officer: Informed

    Why this is correct

    Assigning the security lead as Responsible matches the stem's requirement that they perform the testing, while the project manager as Accountable satisfies their duty to ensure it happens. The compliance officer as Informed reflects their need to receive results without approving or executing the work.

  • ✗

    Security lead: Accountable; Project manager: Responsible; Compliance officer: Informed

    Why it's wrong here

    The stem states the security lead performs the testing, which is Responsible, and the project manager ensures it happens, which is Accountable. Swapping these inverts the doing and owning roles. This assignment would fit a scenario where the project manager personally executes the testing while the security lead owns the outcome.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.