PK0-005 Project Life Cycle Practice Question
During the executing phase, a project manager observes that team members are starting to collaborate and share ideas openly. According to Tuckman's stages of team development, which stage is the team likely in?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Norming
In the norming stage, team members begin to work together and share ideas openly.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Performing
Why it's wrong here
Performing is when the team is highly effective and focused on goals.
- ✗
Forming
Why it's wrong here
Forming is characterized by uncertainty and politeness.
- ✓
Norming
Why this is correct
Norming involves collaboration and open sharing of ideas.
- ✗
Storming
Why it's wrong here
Storming involves conflict and competition.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.