mediumMultiple SelectObjective-mapped
PK0-005 Practice Question: Which TWO tools are commonly used for project…
Which TWO tools are commonly used for project scheduling and displaying task dependencies? (Select TWO)
⚠ Common exam trap
Watch out — candidates often confuse the work breakdown structure (WBS) with a scheduling tool, but the WBS is purely a decomposition of scope, not a timeline or dependency display.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Gantt chart
A Gantt chart is correct because it provides a visual timeline of project tasks, showing start and end dates, durations, and dependencies between tasks through linked bars. This makes it a primary tool for project scheduling and displaying task dependencies in project management.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Gantt chart
Why this is correct
Gantt charts display tasks, durations, and dependencies in a bar chart format.
- ✗
Work breakdown structure
Why it's wrong here
WBS is a hierarchical decomposition, not a scheduling tool.
- ✗
Change log
Why it's wrong here
Change log tracks changes to baselines, not scheduling.
- ✓
Network diagram
Why this is correct
Network diagrams show task sequences and dependencies.
- ✗
Risk register
Why it's wrong here
Risk register is for documenting risks.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.