Courseiva
Project Life CyclemediumMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

A change request is submitted to add a new feature to a project. What is the first step the project manager should take?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Perform impact analysis

The first step is to perform an impact analysis to understand the effects on scope, schedule, cost, etc.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Implement the change

    Why it's wrong here

    Implementation occurs after approval.

  • Perform impact analysis

    Why this is correct

    Impact analysis is the first step in change control.

  • Update the project plan

    Why it's wrong here

    Plan updates happen after approval.

  • Submit to change control board

    Why it's wrong here

    CCB review comes after impact analysis.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.