Courseiva
Project Life CyclemediumMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

In a precedence diagramming method (PDM) network, a successor activity cannot start until its predecessor activity has started. Which type of dependency does this represent?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Start-to-start (SS)

Start-to-start (SS) means the successor cannot start until the predecessor has started.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Start-to-finish (SF)

    Why it's wrong here

    SF means successor cannot finish until predecessor starts.

  • Finish-to-finish (FF)

    Why it's wrong here

    FF means successor cannot finish until predecessor finishes.

  • Finish-to-start (FS)

    Why it's wrong here

    FS means successor cannot start until predecessor finishes.

  • Start-to-start (SS)

    Why this is correct

    SS means successor cannot start until predecessor starts.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.