PK0-005 Practice Question: A project is in the execution phase, and the…

A project is in the execution phase, and the project manager receives a change request to add a new feature that is not in the scope statement. The change request has been approved by the change control board. What must the project manager do next?

⚠ Common exam trap

Watch out — candidates often confuse the sequence of the change control process, thinking a stakeholder meeting to discuss impact is still needed after CCB approval, when in fact the approval itself confirms the impact has been accepted and the next step is to update the plan and baselines.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Update the project management plan and baseline to reflect the approved change.

Once the change control board (CCB) approves a change request, the project manager must formally integrate the approved change into the project by updating the project management plan and the associated baselines (scope, schedule, cost). This ensures that all future project work, performance measurement, and reporting are aligned with the new approved scope, maintaining the integrity of the project's control processes as defined in the PMBOK Guide.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Conduct a meeting with stakeholders to discuss the impact of the change.

    Why it's wrong here

    The impact should have been assessed before approval; now the change is approved and must be implemented.

  • Update the project management plan and baseline to reflect the approved change.

    Why this is correct

    The PM must adjust plans and baselines to incorporate the change and keep the project aligned.

  • Defer the change to the next project phase to minimize disruption.

    Why it's wrong here

    Approved changes should be implemented as planned; deferring may cause issues.

  • Inform the development team to continue with the original scope and ignore the change.

    Why it's wrong here

    Approved changes must be incorporated; ignoring them violates the change control process.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.