Courseiva
hardMultiple Choice

PK0-005 Practice Question: A project manager is working on a construction…

A project manager is working on a construction project and needs to calculate the total float for a non-critical path activity. The activity has an early start of day 5, late start of day 10, early finish of day 15, and late finish of day 20. What is the total float?

⚠ Common exam trap

It's easy for candidates to confuse activity duration (Early Finish minus Early Start) or individual dates (Late Start or Late Finish) with the float calculation, leading candidates to pick 15, 20, or 10 days instead of correctly computing the difference.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

5 days

Total float is calculated as Late Start minus Early Start (or Late Finish minus Early Finish). Here, Late Start (10) minus Early Start (5) equals 5 days. This represents the amount of time the activity can be delayed without affecting the project's overall completion date.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    15 days

    Why it's wrong here

    Fifteen days is the early finish value, not the float; total float is late finish minus early finish (20 − 15 = 5). It is tempting because early finish is a prominent schedule figure and subtracting early start from it gives the activity duration.

  • ✗

    20 days

    Why it's wrong here

    Twenty days equals late finish, not float; total float is late start minus early start (10 − 5 = 5) or late finish minus early finish (20 − 15 = 5). It is tempting because late finish is the largest date in the activity's schedule data.

  • ✓

    5 days

    Why this is correct

    Total float equals late start minus early start, or late finish minus early finish: 10 minus 5, and 20 minus 15, both giving 5 days. This satisfies the calculation requested for the non-critical path activity.

  • ✗

    10 days

    Why it's wrong here

    Ten days is the late start value, not the float; total float is late start minus early start (10 − 5 = 5). It is tempting because the late dates differ from the early dates by five days, and ten is the first late date encountered.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.