Question 166 of 500
Project Management ConceptshardMultiple ChoiceObjective-mapped

Quick Answer

The answer is 5 days. This is correct because total float is calculated by subtracting the early start from the late start, or the early finish from the late finish; here, late start (10) minus early start (5) equals 5 days. Total float represents the amount of time a non-critical activity can be delayed without impacting the project’s overall completion date, making it a key metric for schedule flexibility. On the CompTIA Project+ PK0-005 exam, this concept tests your ability to distinguish between critical and non-critical paths, and a common trap is confusing total float with free float or misapplying the formula to critical path activities, which always have zero float. A reliable memory tip is to think “Late minus Early” for both start and finish—if the result is positive, the activity is non-critical; if zero, it’s on the critical path.

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is working on a construction project and needs to calculate the total float for a non-critical path activity. The activity has an early start of day 5, late start of day 10, early finish of day 15, and late finish of day 20. What is the total float?

Question 1hardmultiple choice
Read the full NAT/PAT explanation →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

5 days

Total float is calculated as Late Start minus Early Start (or Late Finish minus Early Finish). Here, Late Start (10) minus Early Start (5) equals 5 days. This represents the amount of time the activity can be delayed without affecting the project's overall completion date.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 15 days

    Why it's wrong here

    15 is the activity duration, not float.

  • 20 days

    Why it's wrong here

    20 is the late finish, not float.

  • 5 days

    Why this is correct

    Total float = late start - early start = 5 days.

    Related concept

    Read the scenario before looking for a memorised answer.

  • 10 days

    Why it's wrong here

    10 is the difference between late finish and early start, not total float.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is confusing activity duration (Early Finish minus Early Start) or individual dates (Late Start or Late Finish) with the float calculation, leading candidates to pick 15, 20, or 10 days instead of correctly computing the difference.

Detailed technical explanation

How to think about this question

Total float is a critical path method (CPM) metric that applies only to non-critical path activities; critical path activities have zero float. The formula Total Float = Late Start - Early Start (or Late Finish - Early Finish) assumes a forward and backward pass through the network diagram. In real-world construction projects, miscalculating float can lead to improper resource leveling and schedule compression decisions.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: 5 days — Total float is calculated as Late Start minus Early Start (or Late Finish minus Early Finish). Here, Late Start (10) minus Early Start (5) equals 5 days. This represents the amount of time the activity can be delayed without affecting the project's overall completion date.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.