A project manager has identified a stakeholder with high power and high interest. According to the power/interest grid, how should this stakeholder be managed?

⚠ Common exam trap

PK0-005 often tests the power/interest grid by swapping the strategies for high-power/high-interest and high-power/low-interest stakeholders, so candidates must remember that 'manage closely' is for high interest, while 'keep satisfied' is for low interest.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Manage closely

In the power/interest grid, stakeholders with both high power and high interest are the most critical group because they can significantly influence the project and care deeply about its outcomes. The recommended strategy is to 'manage closely,' which means engaging them frequently, involving them in decision-making, and providing detailed, timely communication. This ensures their concerns are addressed and their influence is leveraged positively.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Monitor

    Why it's wrong here

    Monitoring suits low-power, low-interest stakeholders who require minimal effort and occasional status updates. A high-power, high-interest stakeholder must be managed closely and engaged directly, because their influence and concern can shape project direction. Monitoring leaves such a stakeholder uninvolved and their expectations unmanaged.

  • ✗

    Keep informed

    Why it's wrong here

    High power combined with high interest demands active engagement and close collaboration, since these stakeholders can materially affect the project and care about outcomes. Keeping them informed suits low-power, high-interest parties who merely need updates. Here, passive communication leaves a decisive stakeholder's concerns unaddressed.

  • ✗

    Keep satisfied

    Why it's wrong here

    Keeping satisfied applies to high-power, low-interest stakeholders whose support is needed but who do not want detailed involvement. A high-interest stakeholder expects active collaboration and two-way dialogue, so limiting engagement to satisfaction management ignores their stake and risks late objections that could derail the project.

  • ✓

    Manage closely

    Why this is correct

    High power combined with high interest places the stakeholder in the grid's manage-closely quadrant, requiring active, regular engagement. Their ability to influence the project and their investment in outcomes mean their concerns must be addressed continuously to avoid disruption.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.