Courseiva
Project Life CyclemediumMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

Which type of contract places the greatest cost risk on the seller?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Fixed-price contract

Fixed-price contract places cost risk on the seller because the price is fixed regardless of actual costs.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Cost plus incentive fee

    Why it's wrong here

    Still cost-reimbursable; risk on buyer.

  • Fixed-price contract

    Why this is correct

    Seller bears cost risk in fixed-price.

  • Time and materials contract

    Why it's wrong here

    T&M shares risk.

  • Cost-reimbursable contract

    Why it's wrong here

    Cost-reimbursable places risk on buyer.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.