PK0-005 Project Management Concepts Practice Question
Which of the following is a key responsibility of the project sponsor?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Providing resources and removing obstacles
The project sponsor provides resources, champions the project, and resolves escalations. The PM plans and executes; the team does tasks; the steering committee provides governance.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Performing quality assurance
Why it's wrong here
Quality assurance is often done by the PM or quality team.
- ✗
Developing the project schedule
Why it's wrong here
This is typically the project manager's responsibility.
- ✓
Providing resources and removing obstacles
Why this is correct
Correct. The sponsor provides funding, resources, and support.
- ✗
Executing project tasks
Why it's wrong here
This is the project team's responsibility.
Visual reference
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.