Question 291 of 500
Project Management ConceptshardMultiple ChoiceObjective-mapped

Quick Answer

The answer is to initiate the change control process. This is correct because any request that impacts the project’s scope, resources, or timeline—like a new feature requiring additional resources and an extended schedule—must be formally evaluated through the defined change control process for out of scope requests. On the CompTIA Project+ PK0-005 exam, this scenario tests your understanding of scope management and the critical distinction between a formal change request and uncontrolled scope creep. A common trap is to assume the project manager can approve the change directly or simply say no, but the exam emphasizes that all scope-altering demands must be documented, assessed for impact, and approved by the change control board (CCB) before implementation. Remember the memory tip: “If it changes scope, time, or cost—stop and submit a change request.”

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During project execution, a key stakeholder demands a feature that was not included in the original scope. The project manager determines that the feature would require additional resources and extend the timeline. Which of the following is the BEST course of action?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "best"

    Why it matters: Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Initiate the change control process

The correct answer is D because any change that impacts scope, resources, or timeline must go through the formal change control process as defined in the project management plan. This ensures that all changes are evaluated for impact, approved by the change control board (CCB), and properly documented before implementation. Skipping this process introduces uncontrolled scope creep and risks project failure.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the project scope without formal approval

    Why it's wrong here

    Incorrect. Updating scope without approval undermines control and may lead to unauthorized changes.

  • Implement the feature to satisfy the stakeholder

    Why it's wrong here

    Incorrect. Implementing without formal approval violates change control and may cause scope creep.

  • Reject the request because it is out of scope

    Why it's wrong here

    Incorrect. Out-of-scope requests should be processed through change control, not immediately rejected.

  • Initiate the change control process

    Why this is correct

    Correct. The change control process evaluates the impact and obtains approval before changes are made.

    Clue confirmation

    The clue word "best" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

CompTIA often tests the misconception that satisfying a key stakeholder immediately is more important than following formal processes, leading candidates to choose Option B, but the correct approach is to initiate the change control process to evaluate and approve the change properly.

Detailed technical explanation

How to think about this question

The change control process typically involves submitting a change request, performing an impact analysis (cost, schedule, quality, risk), and obtaining formal approval from the CCB before any changes are integrated into the baseline. In the PMBOK framework, this is part of the Perform Integrated Change Control process, which ensures that only approved changes are implemented and that the project remains aligned with its objectives. Real-world example: a software project adding a new API endpoint without change control could break existing integrations and require unplanned regression testing, delaying the release.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Initiate the change control process — The correct answer is D because any change that impacts scope, resources, or timeline must go through the formal change control process as defined in the project management plan. This ensures that all changes are evaluated for impact, approved by the change control board (CCB), and properly documented before implementation. Skipping this process introduces uncontrolled scope creep and risks project failure.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "best". Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on PK0-005

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A project manager is leading a software development project that has a fixed budget and strict deadline. During the execution phase, the development team identifies a critical security vulnerability that requires immediate remediation, which will add two weeks to the schedule and increase costs by 10%. What is the BEST course of action for the project manager?

medium
  • A.Escalate the issue to the project sponsor with a trade-off analysis of cost, schedule, and scope impacts.
  • B.Reduce the scope by removing one feature to compensate for the additional work.
  • C.Proceed with the original plan and document the vulnerability as a known risk.
  • D.Instruct the team to fix the vulnerability immediately and then inform the sponsor of the changes.

Why A: Option A is correct because the project manager must balance the triple constraint (cost, schedule, scope) when an unplanned security vulnerability emerges. Escalating to the sponsor with a trade-off analysis allows informed decision-making, as the fixed budget and strict deadline mean any change requires stakeholder approval. This aligns with PMI's best practices for managing change requests in a constrained environment.

Keep practising

More PK0-005 practice questions

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.