hardMultiple SelectObjective-mapped
PK0-005 Practice Question: Which TWO items are typically included in a…
Which TWO items are typically included in a project closure report?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Final project performance summary
Options C and D are correct. A project closure report typically includes a final project performance summary and lessons learned. The risk register (A) is archived separately, the project schedule (B) is part of the project management plan, and the stakeholder engagement plan (E) is a separate document not included in the closure report.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The risk register
Why it's wrong here
Archived separately.
- ✗
The project schedule
Why it's wrong here
Part of planning documents.
- ✓
Final project performance summary
Why this is correct
Key closure report content.
- ✓
Lessons learned
Why this is correct
Key closure report content.
- ✗
The stakeholder engagement plan
Why it's wrong here
Not part of closure report.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.