PK0-005 Project Management Concepts Practice Question
A project manager is leading a team to develop a new mobile application. The project has a fixed budget and a strict deadline. During the execution phase, the stakeholder requests additional features that were not originally planned. Which project constraint is most directly affected by this request?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Scope
Adding features without adjusting time or cost increases scope, leading to scope creep. This directly affects the scope constraint.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Quality
Why it's wrong here
Quality is not the primary constraint; scope change is the direct issue.
- ✓
Scope
Why this is correct
Uncontrolled changes to requirements are scope creep, directly affecting scope.
- ✗
Schedule
Why it's wrong here
Schedule may be affected, but the direct impact is scope increase.
- ✗
Cost
Why it's wrong here
Cost may be affected, but the primary immediate impact is on scope.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.