PK0-005 Project Life Cycle Practice Question
During project planning, a project manager is decomposing the project scope into smaller components. Which document is being created, and what is the lowest level of decomposition called?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Work breakdown structure (WBS); work package
The WBS is created, and the lowest level is a work package.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Network diagram; activity
Why it's wrong here
A network diagram shows activity dependencies, not scope decomposition.
- ✓
Work breakdown structure (WBS); work package
Why this is correct
The WBS is decomposed into work packages at the lowest level.
- ✗
Project charter; work item
Why it's wrong here
The project charter is created during initiating, not planning.
- ✗
Risk register; risk event
Why it's wrong here
The risk register is for risk identification, not scope decomposition.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.