Courseiva
Project Life CyclemediumMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

During project planning, a project manager is decomposing the project scope into smaller components. Which document is being created, and what is the lowest level of decomposition called?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Work breakdown structure (WBS); work package

The WBS is created, and the lowest level is a work package.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Network diagram; activity

    Why it's wrong here

    A network diagram shows activity dependencies, not scope decomposition.

  • Work breakdown structure (WBS); work package

    Why this is correct

    The WBS is decomposed into work packages at the lowest level.

  • Project charter; work item

    Why it's wrong here

    The project charter is created during initiating, not planning.

  • Risk register; risk event

    Why it's wrong here

    The risk register is for risk identification, not scope decomposition.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.