PK0-005 Tools and Documentation Practice Question
A project team is using Jira for an Agile project. Which TWO artefacts are typically managed within Jira for sprint planning and tracking? (Choose two.)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Product backlog
Jira supports product backlog (epics, stories, tasks) and sprint backlog (selected items for current sprint). Velocity is a metric, not an artefact; burndown chart is a visualization; stakeholder register is not typically in Jira.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Product backlog
Why this is correct
Jira manages the product backlog with user stories and epics.
- ✗
Burndown chart
Why it's wrong here
Burndown charts are visual reports, not artefacts that are 'managed' like backlogs.
- ✗
Stakeholder register
Why it's wrong here
Stakeholder register is typically maintained in a document or spreadsheet, not in Jira.
- ✗
Velocity
Why it's wrong here
Velocity is a metric derived from completed story points, not a managed artefact.
- ✓
Sprint backlog
Why this is correct
The sprint backlog contains items committed for the sprint, tracked in Jira.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.