Question 48 of 500
Project Life Cycle PhaseseasyMultiple SelectObjective-mapped

Quick Answer

The correct answer is developing the project charter and identifying stakeholders, as these are the two key activities performed during the Initiating phase of a project. This phase formally authorizes the project or a new phase, with the project charter serving as the foundational document that grants the project manager authority and resources. Identifying stakeholders ensures all parties affected by or involved in the project are recognized early, setting the stage for effective communication and engagement. On the CompTIA Project+ PK0-005 exam, this concept tests your ability to distinguish Initiating activities from those in Planning or Closing, a common trap being the inclusion of defining scope or creating a WBS, which belong to Planning. A reliable memory tip is to think of the Initiating phase as the "green light" moment: you get the charter signed and know who is in the room, but you do not yet plan the work.

PK0-005 Project Life Cycle Phases Practice Question

This PK0-005 practice question tests your understanding of project life cycle phases. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which TWO of the following are key activities performed during the Initiating phase of a project?

Question 1easymulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Identify stakeholders

Identifying stakeholders and developing the project charter are key activities in Initiating. Defining the project scope occurs later in Planning, and creating the WBS is also a Planning activity. Obtaining formal acceptance is Closing.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Define project scope

    Why it's wrong here

    Defining scope is part of Planning.

  • Identify stakeholders

    Why this is correct

    Stakeholder identification is a key initiating process.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Obtain formal acceptance of deliverables

    Why it's wrong here

    Formal acceptance occurs in Closing.

  • Create work breakdown structure

    Why it's wrong here

    WBS is created during Planning.

  • Develop project charter

    Why this is correct

    The project charter authorizes the project and is created in Initiating.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PK0-005 exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Life Cycle Phases — This question tests Project Life Cycle Phases — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Identify stakeholders — Identifying stakeholders and developing the project charter are key activities in Initiating. Defining the project scope occurs later in Planning, and creating the WBS is also a Planning activity. Obtaining formal acceptance is Closing.

What should I do if I get this PK0-005 question wrong?

Identify which PK0-005 exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PK0-005

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which TWO of the following activities are typically performed during the initiation phase of a project?

easy
  • A.Define project scope
  • B.Develop the project schedule
  • C.Develop the project charter
  • D.Create the work breakdown structure
  • E.Identify stakeholders

Why C: Developing the project charter and identifying stakeholders are initiation phase activities. Creating the WBS, developing the schedule, and defining scope are planning phase activities.

Variation 2. Which TWO activities are typically performed during the initiation phase of a project?

medium
  • A.Develop the project charter
  • B.Develop the project schedule
  • C.Identify stakeholders
  • D.Develop the work breakdown structure
  • E.Create the risk response plan

Why A: Options C and D are correct. The initiation phase includes identifying stakeholders and developing the project charter. Option A is incorrect because the WBS is created in planning. Option B is incorrect because the risk response plan is created in planning. Option E is incorrect because the schedule is developed in planning.

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.