Which TWO of the following are key activities performed during the Initiating phase of a project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Identify stakeholders
Identifying stakeholders and developing the project charter are key activities in Initiating. Defining the project scope occurs later in Planning, and creating the WBS is also a Planning activity. Obtaining formal acceptance is Closing.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Define project scope
Why it's wrong here
Defining scope is part of Planning.
- ✓
Identify stakeholders
Why this is correct
Stakeholder identification is a key initiating process.
- ✗
Obtain formal acceptance of deliverables
Why it's wrong here
Formal acceptance occurs in Closing.
- ✗
Create work breakdown structure
Why it's wrong here
WBS is created during Planning.
- ✓
Develop project charter
Why this is correct
The project charter authorizes the project and is created in Initiating.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
2 more ways this is tested on PK0-005
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which TWO of the following activities are typically performed during the initiation phase of a project?
easy- A.Define project scope
- B.Develop the project schedule
- ✓ C.Develop the project charter
- D.Create the work breakdown structure
- ✓ E.Identify stakeholders
Why C: Developing the project charter and identifying stakeholders are initiation phase activities. Creating the WBS, developing the schedule, and defining scope are planning phase activities.
Variation 2. Which TWO activities are typically performed during the initiation phase of a project?
medium- ✓ A.Develop the project charter
- B.Develop the project schedule
- ✓ C.Identify stakeholders
- D.Develop the work breakdown structure
- E.Create the risk response plan
Why A: Options A and C are correct. The initiation phase includes developing the project charter and identifying stakeholders. Option B is incorrect because the project schedule is developed during planning. Option D is incorrect because the work breakdown structure is created during planning. Option E is incorrect because the risk response plan is created during planning.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.