A project manager uses a tool that shows the sequence of project activities and their dependencies. Which tool is this?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Network diagram
A network diagram shows activity sequence and dependencies. Option A is wrong because a resource histogram shows resource allocation. Option C is wrong because a WBS is hierarchical. Option D is wrong because a Gantt chart shows a bar chart schedule, not dependencies.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Resource histogram
Why it's wrong here
A resource histogram shows resource allocation over time.
- ✓
Network diagram
Why this is correct
A network diagram shows activity sequence and dependencies.
- ✗
Work breakdown structure
Why it's wrong here
A work breakdown structure is a hierarchical decomposition of work.
- ✗
Gantt chart
Why it's wrong here
A Gantt chart shows a bar chart schedule, not dependencies.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.